Project Value
$850K
- Site geotechnical investigations
- RPEQ engineering design and certification
- Detailed design documentation
- Design and construction of two new composite bridges
- Demolition and removal of existing bridges
- Installation of new bridge and balustrades
- Installation of adjoining concrete pathways
- Establishment/maintenance period
- Under bridge pipe work including trenching and fitting to existing water services
![](https://www.tlcc.net.au/wp-content/uploads/2022/08/TLCC-Redlands-Pedestrian-Bridge-02.jpg)
THE PROJECT INCLUDED THE REMOVAL OF TWO PEDESTRIAN BRIDGES AND THE INSTALLATION OF TAILOR-MADE REPLACEMENTS
![](https://www.tlcc.net.au/wp-content/uploads/2022/08/TLCC-Redlands-Pedestrian-Bridge-03.jpg)
![](https://www.tlcc.net.au/wp-content/uploads/2022/08/TLCC-Redlands-Pedestrian-Bridge-04.jpg)
![](https://www.tlcc.net.au/wp-content/uploads/2022/08/TLCC-Redlands-Pedestrian-Bridge-06.jpg)
![](https://www.tlcc.net.au/wp-content/uploads/2022/08/TLCC-Redlands-Pedestrian-Bridge-05.jpg)