By Moreton Bay Regional Council

Caboolture, QLD

Moreton Bay Regional Council engaged TLCC as the principal contractor (PCBU) for improvement works on the Del Rosso Drainage Channel in Caboolture – 50km north of Brisbane. The project involved stripping the existing channel and installing environmental controls to improve the quality of the water leaving the channel before it enters the main stormwater system.

Completion: TBC

Del Rosso Rd Drainage Environment & Government Project TLCC
Project Value $180K
  • Traffic and pedestrian management
  • Earthworks (cut and fill, final trim, ripping/cultivation and amelioration)
  • Granite boulders
  • Sandstone boulders
  • Rock armour
  • Landscape soil and mulch
  • Planting and turfing
  • Erosion control matting
  • Installation of large embedded logs and root ball stumps
Del Rosso Rd Drainage Environment & Government Project TLCC
Del Rosso Rd Drainage Environment & Government Project TLCC